DCP-106
Visibility to DCUSA Parties Regarding Applications to the Authority by DNO’s to Change Allowed Revenue
DCP106 - 'Visibility to DCUSA Parties Regarding Applications to the Authority by DNO's to Change Allowed Revenue' was raised as Suppliers do not receive notice of applications by DNOs to Ofgem to increase/decrease their allowed revenue. These applications to Ofgem, if approved, may result in tariff changes. The CP will require DNOs to provide transparency and advanced information to DCUSA Parties of their application to Ofgem for extraordinary changes to revenue and the implementation dates that have been requested.