342 - Removal of residual charging for storage facilities in the EDCM
- CP Number 342
- Proposing Company ELECTRICITY NORTH WEST LIMITED
- Raised Date 31/01/2019
- Expected Implementation Date 01/04/2021
- Implementation Date 01/04/2021
- Status Implemented
- Urgent No
- Last Updated 01/04/2021
- Secretariat Support Dylan Townsend
-
Synopsis
The intent of this Change Proposal is to amend the application of residual charging in respect of storage generators in the EDCM
Initial Assessment
Definition
Consultation
Change Report
Voting
Approved (Awaiting Implementation)
Implemented
Related Activities
Related Groups
Name | Committee Status |
---|---|
DCP 342 Working Group | Ceased |