DCP-265
High Cost Cap/Voltage Rule Precedence – revision to Schedule 22 of the DCUSA (the Common Connection Charging Methodology)
DCP265 - High Cost Cap/Voltage Rule Precedence - revision to Schedule 22 of the DCUSA (the Common Connection Charging Methodology)||This Change Proposal (CP) seeks to update the Common Connection Charging Methodology (CCCM) to clarify which of the £200/kW rule (the High Cost Cap) set out under paragraph 1.15 of Schedule 22 of the DCUSA and the voltage rule set out under paragraph 1.30 of Schedule 22 of the DCUSA, takes precedence when both apply.||The implementation date proposed is the first DCUSA release following approval on the 30 June 2016.