350 - Creation of Embedded Capacity Registers
- CP Number 350
- Proposing Company UK POWER RESERVE LIMITED
- Raised Date 17/07/2019
- Expected Implementation Date 19/06/2020
- Implementation Date 11/07/2020
- Status Implemented
- Urgent No
- Last Updated 11/07/2020
- Secretariat Support Richard Colwill
-
Synopsis
The change seeks to require each DNO and IDNO to create a public register of all sites that use their networks and influence the operation of the GB power market. The Register would contain details of each connected site and would be kept up to date by each DNO and IDNO.
Initial Assessment
Definition
Consultation
Voting
Awaiting Consent
Approved (Awaiting Implementation)
Implemented
Related Activities
Related Committee & Group | Title | Number | Date | Location |
---|---|---|---|---|
DCP 350 Working Group | DCP 350 Authority Decision | - | 01/07/2020 | - |
DCP 350 Working Group | DCP 350 Change Declaration | 001 | 05/05/2020 | - |
DCP 350 Working Group | DCP 350: Creation of Embedded Capacity Registers | - | 17/04/2020 | - |
DCP 350 Working Group | DCP 350 Working Group – Meeting 05 | 005 | 09/03/2020 | By Web Conference |
DCP 350 Working Group | DCP 350 Consultation | - | 06/02/2020 | - |
DCP 350 Working Group | DCP 350 Working Group – Meeting 04 | 004 | 20/01/2020 | By Web Conference |
DCP 350 Working Group | DCP 350 Working Group – Meeting 03 | 003 | 29/11/2019 | By Web Conference |
DCP 350 Working Group | DCP 350 Working Group – Meeting 02 | 002 | 08/10/2019 | Meeting Room 10, Bloomsbury Way, The Bloomsbury Building, 10 Bloomsbury Way, London, WC1A 2SL |
DCP 350 Working Group | DCP 350 Working Group – Meeting 01 | 001 | 28/08/2019 | By Web Conference |