350 - Creation of Embedded Capacity Registers

  • CP Number 350
  • Proposing Company UK POWER RESERVE LIMITED
  • Raised Date 17/07/2019
  • Expected Implementation Date 19/06/2020
  • Implementation Date 11/07/2020
  • Status Implemented
  • Urgent No
  • Last Updated 11/07/2020
  • Secretariat Support Richard Colwill
  • Synopsis

    The change seeks to require each DNO and IDNO to create a public register of all sites that use their networks and influence the operation of the GB power market. The Register would contain details of each connected site and would be kept up to date by each DNO and IDNO.