333 - Appropriate treatment and allocation of eligible use of system bad debt costs

  • CP Number 333
  • Proposing Company NORTHERN POWERGRID (NORTHEAST) PLC
  • Raised Date 12/11/2018
  • Expected Implementation Date 01/04/2021
  • Implementation Date 01/04/2021
  • Status Implemented
  • Urgent No
  • Last Updated 01/04/2021
  • Secretariat Support Huw Neyroud
  • Change Proposer Lee Wells
  • Synopsis

    DCP333 - Appropriate treatment and allocation of eligible use of system bad debt costs. The intent of this Change Proposal is to ensure that associated costs are recovered fairly and equitable from customers where a DNO or IDNO Party incurs eligible use of system bad debt due to insolvency of electricity suppliers whose supply licence has subsequently been revoked.

Initial Assessment
Consultation
Change Report
Voting
Awaiting Consent
Approved (Awaiting Implementation)
Implemented

Related Groups

Name Committee Status
DCP 333 Working GroupLive