402 - Amendment to the ‘Effective From’ Date of DCP 349

  • CP Number 402
  • Proposing Company ELECTRICITY NORTH WEST LIMITED
  • Raised Date 09/03/2022
  • Expected Implementation Date 23/06/2022
  • Implementation Date 23/06/2022
  • Status Approved (Awaiting Implementation)
  • Urgent No
  • Last Updated 14/04/2022
  • Secretariat Support Richard Colwill
  • Change Proposer Andrew Sherry
  • Synopsis

    To amend the ‘effective from’ date currently set in the DCP 349 legal text, which has been approved to be implemented on 01 April 2022, from 24 June 2022 to 29 June 2023. This allows for a transition time of a minimum of 12 months for existing Suppliers to move to the new requirements.

Initial Assessment
Change Report
Voting
Approved (Awaiting Implementation)