329 - Amend Requirements for Emergency De-energisation in Schedule 2B – National Terms of Connection

  • CP Number 329
  • Proposing Company ELECTRICITY NORTH WEST LIMITED
  • Raised Date 21/09/2018
  • Expected Implementation Date 07/11/2019
  • Implementation Date 07/11/2019
  • Status Implemented
  • Urgent No
  • Last Updated 07/11/2019
  • Secretariat Support Richard Colwill
  • Change Proposer Andrew Sherry
  • Synopsis

    DCP329 - Amend Requirements for Emergency De-energisation in Schedule 2B - National Terms of Connection||The intent of this Change Proposal is to revise/amend the National Terms of Connection, to allow for the De-energisation of a Customer’s Installation by the Customer without the need to obtain prior agreement from the Licenced Distributor, where the condition or manner of operation of the Distribution System or the connection equipment poses an immediate threat of injury or material damage to any person or property. ||

Initial Assessment
Definition
Consultation
Change Report
Voting
Awaiting Consent
Approved (Awaiting Implementation)
Implemented

Related Activities

Related Groups

Name Committee Status
DCP 329Live