Skip to main content

Change Register

407 - Access SCR: Speculative Development

  • CP Number 407
  • Proposing Company ELECTRICITY NORTH WEST LIMITED
  • Raised Date 06/05/2022
  • Expected Implementation Date 01/04/2023
  • Status Definition
  • Urgent Yes
  • Last Updated 11/05/2022
  • Secretariat Support Melissa Kendal
  • Change Proposer Brian Hoy
  • Synopsis

    The purpose of this change proposal (CP) is to implement parts of Ofgem’s Access SCR Decision in respect of Speculative Developments into the Common Connections Charging Methodology (CCCM) and consequential changes into Schedule 32 (Residual Charging Bands). This CP seeks to address paragraph 16 of the Access SCR Direction.

Initial Assessment
Definition
Consultation
Change Report
Voting
Awaiting Consent
Approved (Awaiting Implementation)
Implemented

Related Activities

Related Groups

Name Committee Status
DCP 407 Working GroupLive

Related Documents